FINAL WITH ANSWERS 1.Which of the following is considered a major process flow structure? Lead Time Fabrication Lean Manufacturing Project 2.ISO audits result in certifications that are done by f
FINAL WITH ANSWERS 1.Which of the following is considered a major process flow structure? Lead Time Fabrication Lean Manufacturing Project 2.ISO audits result in certifications that are done by f
(CCR)? (Enterprise (Master (Material (Work (plan, (statistical 1.Which 10,000 10. 11. 12. 13. 14,000 14. 14000 15. 16. 17. 18. 19. 1st 2.ISO 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. 2nd 3.Which 30. 3rd 4,000 4,000? 4. 5. 6,000 6. 7.Which 8. 9. A According Agile An Application Blocking Breakage Breakdown Buffering Build Certification Competitor Concentrate Considering Continuous Control Cost Current Cycle Cyclical Decision Deming’s Design Designing Determining Discovery Dividends Do Dr. During ERP Economies Efficient Eli Eliminate Environmental Estimating Events Fabrication Flow Forecasting Forward Future Gantt Gap Goldratt's Group Hau Have ISO If In Inoperable Introduce Inventory Kanban Keep Lead Lean Lee’s Level Leverage Look MPS MRP Manufacturing Market Minimized Operating Order PDCA Pareto Party Past Pedigree People Plan) Planning) Product Production Project Quality Quantity Redesign Reducing Requirements Resource Return Revenue Risk Run SQC Sales Schedule) Services Shingo Sigma Simplification Six Six-Sigma Slow Staging Standard Starving Statistical Structure) Sub-jobs Success Task Tasks Teamwork The There Time Tools Tree Trust Typing Utilization Utilize WBS What Which Work a ability act) activation activities actually addresses against agency aggregate ahead all allow alone. an analysis analytical and annual another any applications are as assembled? assembly assuming at audit auditor audits availability available axis based basis be because behavior being best better blueprint, bottleneck bottlenecks bottlenecks. broken businesses by can cannot capacity capacity-constrained capital care cases, certification certifications chain chains, characteristic chart charting charts check, classified classify classifying coming component components components. concerned conditions consider considered constraints, consulting control control). control. controls correct cost cost? current curve customer cycle defects delivers demand demand? describes design developed developing development development? deviation discounts distinguishes diverts do do, does done down down, dues. during each economic effective efficiencies element elements elimination emphasizing employee employees employees. enables end entrepreneurial. equipment evolving expenses external factor factors factory factory, far financial firm firm's firm? first, flow flow. focus following following: following? for frame framework from functional given goods. govern gross guide hand has health hedging high holding hour if impact implementation improvement improvements in included increase independently. inexpensively inherent inherently intensive internal international into inventoried. inventory investment is it its itself kit? lean learning legal length levels line. loading looking lose lower major make making management manager manufactured manufacturing many markers materials means measure measurements minimum mitigate money? more most moving must national net no not number of office, on one operation operation? operations operations. operations; optimized or order organization. organization? organizational organizations. out output over overseeing package packages parties. parts patient pay payoff perform physical physical, placing plan planning plant point poka-yokes poka-yokes? prescribes prevent price primarily primary principle? principles procedural, process process. product production production? products products? program programs? project project, protection qualified quality quantity queue? rapidly rates rather reasonable reducing reengineering? removing represents requirement resource result rules run same same. sampling saved scale scheduling scope scrap. second, segmented select separate serves service service. services services. several shape should similar. situation size skills slows so software sought source specifically, speeding spends spent stage standards standards/certifying starting states stop stops, stream stream. structure? subcontractor such supplier suppliers supply switch system systems? technical technology technology? term terms than that the theory there they third those three-T's time times to together tool tools trees uncertainty under underlies unit until up use used using usually value value-adding velocity. vertical virtual waiting waste waste. way what when where whether which who will with with? within work work? worked workforce would you – •
1.Which of the following is considered a major process flow structure?
Lead Time
Fabrication
Lean Manufacturing
Project
2.ISO audits result in certifications that are done by first, second, or third parties. Which of the following result in the best certification of a firm?
Certification is sought by any firm assuming they pay annual dues.
2nd Party – where a customer audits its supplier
3rd Party – where a qualified national or international standards/certifying agency serves as an auditor
1st Party – where a firm audit itself against ISO standards